Ferrous Metalworks
Yaxbe · QBR — Cirrus ERP Migration
Confidential
Generated 2026-06-01
Generated 2026-06-01
Scope: Cirrus ERP MigrationPeriod: Engagement to date (Mar 30, 2026 – Jun 1, 2026)By: leaderLenses: QBR
Client objectives
Migrate financial consolidation and inventory management onto a single ERP instance across three plants.
1 win this quarter
Evidence-based, drawn directly from this quarter's delivery data:
- Projected to land 65–65% under the contracted budget.
Honest challenge
The "Plant 2 inventory reconciliation sign-off" criterion on Plant 2 inventory reconciliation was sent back for changes.
- Incorporating the requested changes and resubmitting for review.
The metrics that matter
Schedule adherence
Not yet available
Budget used
16%
est · 45% of timeline elapsed
Benefits realized
Not yet realized
vs committed 120,000
Next quarter
The remaining planned phases:
- Build — target Jun 22, 2026
- Cutover prep — target Aug 3, 2026
- Hypercare — target Aug 17, 2026